Initial Project Cost$1,500,000
Completion Cost$850,000
Scheduled Completion DateFebruary 2013
Actual Completion DateJanuary 2013
OwnerTom Fante (Retired)
SJUSD
(916) 903-6303

Construction scope of work to be completed in 156 days included:

Through an in-depth value engineering session, ICS and the architect were able to evaluate alternative materials, adding value and quality to the project, while saving a substantial amount of bond funds.