Sierra Oaks Elementary School

Sierra Oaks - Elementary School

New Classroom Wing

Lease – Leaseback

Initial Project Cost$1,800,000
Completion Cost$1,600,000
Scheduled Completion DateDecember 2011
Actual Completion DateNovember 2011
OwnerKent Kern
SJUSD
(916) 971-5796

Construction scope of work to be completed in 109 days included:

ICS assumed the responsibility of managing this project from a different construction management firm within the district, and by re-evaluating scope and site specific needs, was able to immediately save $750,000 in the budget.