Site icon Innovative Construction Services, Inc.

Project Frog

Project Frog

Del Dayo Elementary and Mariemont Elementary

New Classroom

Lease – Leaseback

Initial Project Cost$1,592,205
Completion Cost$1,554,344
Scheduled Completion Date August 2016
Actual Completion Date August 2016
OwnerKent Kern
SJUSD
(916) 971-5796

Construction of a new Classroom approximately 2,700 SF including:

This project was a Lease-Leaseback Delivery Method. The value of the Lease Agreement was $1,592,205. Returned to the Owner Unused/Saved project funds $37,861.

Watch Del Dayo Time-Lapse videos at the ICS YouTube channel  https://www.youtube.com/channel/UCPQm5bRfMIAGwLgBk7ezSkQ

 