Andrew Carnegie Middle School

Andrew Carnegie Classroom & Weight Room

New Classroom Wing & Weight Room

Design, Bid and Build

Initial Project Cost$2,300,000
Completion Cost$2,100,000
Scheduled Completion DateAugust 2010
Actual Completion DateAugust 2010
OwnerKent Kern
SJUSD
(916) 971-5796

Construction scope of work in 138 days completed:

Original contract amount $1,600,000

Change order percentage 1.4%

The total project budget was $2.3 million. ICS returned $220,000 to the District.